APS system that creates production schedules
at high speed for multiple items and multiple processes
Q:How to specify a setup time for changing a sub resource
A:
Steps:
1,In the resource setup table, specify the resource that requires a setup in the "Resource" field.
2,In the "Resource L" and "Resource R" fields of the same table, enter a combination of resources.
3,In the "Setup time" field of the same table, specify a setup time in minutes.