APS system that creates production schedules
at high speed for multiple items and multiple processes
Q:How to split an operation by specifying a split number
A:
Steps:
1.Right-click on the operation you want to split and select [Operation] - [Edit Operation...] from the popup menu.
2.Specify a split number for the property "Split number" in the Split tab of the properties window.
3.If you reschedule, the operation will be split and assigned according to the specified split number.