Q:How to specify the scheduling basis time

A:

Steps:

1.Click on the [Project Settings] button on the toolbar or select [Schedule] - [Project Settings...] from the menu. In the properties window, select the Time periods tab and click on the [...] button to display the time settings dialog.
2.In the Time Settings Dialog, specify an absolute time or a relative time.