Q:How to specify that operations will be assigned to a resource according to the resource quantity of that resource

A:

Steps:

1.In the resource table, set the property "Resource quantity constraints" of the target resource to "According to resource quantity".

When the property "Resource quantity constraints" of a resource is set to "According to resource quantity", production time will be changed according to the available resource quantity at the time to which the operation is assigned.