Q:How to assign operations in a way that they cannot be suspended over a non-working time period
A:
Steps:
1.In the resource Gantt chart or the resource table, select a resource for which you want to specify the Production suspend time MAX.
2.Select the Settings tab of the properties window.
3.Specify -1 for the property "Production suspend time MAX".
Depending on the value you specify for the property "Production suspend time MAX", the setting will have the following meanings.
-1 ..... Does not allow the operation to straddle non-working time.
0 ..... Allows an operation to straddle non-working time.
Positive integer ..... Indicates the maximum amount of time (in minutes) that an operation can be suspended.