Q: How to constrain the maximum amount that a furnace resource can process at once by production quantity

A:

Steps:

1.In the resource table, set the "Assigned resource quantity flag" to "1" (proportionate to production quantity).
2.In the calendar table, enter the maximum production quantity by resource quantity in the "Shift codes" field. *1
*1. The resource quantity will be used as much as the result of multiplying the production quantity of an operation by the required resource quantity of a master use instruction.