Q:How to specify to occupy a tank for 3 hours after the end of an operation
A:
Steps:
1.In the resource table, specify the time to lock the target resource in the "Resource lock time" field of that resource.
2.In the project settings, check the property "Enable resource lock" displayed in the Settings tab.