APS (Advanced Planning and Scheduling) Asprova APS

 
Home > FAQ > Use instructionsHow to schedule workers
FAQ
[[ Use instructions ]]

How to schedule workers

Search in FAQ:

Q:How to schedule workers

A:

Steps:

1.Select the Integrated Master.
2.Add a use instruction to the process that requires a worker.
3.Specify "S0" in the "Instruction code" field.
4.Specify the resource code of the worker in the "Resource/Item" field.
5.Specify "0" in the "Production" field.

* For the instruction code "S0", 10 codes from S0 to S9 are recognized as sub resources by default. You can also use other strings for sub resources by changing the settings of the use instruction master.


>>Back To [ Use instructions ]