APS system that creates production schedules
at high speed for multiple items and multiple processes
Q:How to assign multiple workers to one operation
A:
Steps:
1.In the resource table in which setup workers are specified, set the property "Resource quantity constraints" to "Constrained".
2.Instruction type of the Integrated Master: Specify a velue for the property "Required resource quantity" of the use instruction so that the target number of workers are assigned to the resource.
Also, you can specify workers as sub resources. Resources for which the instruction code Sn is specified are called sub resources. Sub resources are assigned to the same time as the corresponding main resources are assigned.