APS (Advanced Planning and Scheduling) Asprova APS

 
Home > FAQ > Use instructionsHow to specify the maximum quantity that a certain combination of an item and a resource can produce at once
FAQ
[[ Use instructions ]]

How to specify the maximum quantity that a certain combination of an item and a resource can produce at once

Search in FAQ:

Q:How to specify the maximum quantity that a certain combination of an item and a resource can produce at once

A:

Steps:

1.Instruction type of the Integrated Master: Specify the above-stated maximum quantity in the "Operation split size MAX" field of the use instruction.

If you specify 0 for "Operation split size MAX", there will be no quantity constraint. If the production quantity of an operation is larger than the operation split size MAX, the operation will be automatically split.



>>Back To [ Use instructions ]