Q:How to specify the scheduling basis time
A:
Steps:
1.Click on the [Project Settings] button on the toolbar or select [Schedule] - [Project Settings...] from the menu. In the properties window, select the Time periods tab and click on the [...] button to display the time settings dialog.
2.In the Time Settings Dialog, specify an absolute time or a relative time.
Q:How to forcibly make a setup time 0 between same items
A:
Steps:
1.Click on the [Project Settings] button on the toolbar. Or, select [Schedule] - [Project Settings...] from the main menu. Properties for the project settings will be displayed in the properties window.
2.Select the Settings tab from the properties window. Properties of the settings will be displayed in the properties window.
3.Check the property "Zero setup time between same items".
Q:How to change the day demarcation time to 9:00
A:
Steps:
1.Select [Schedule] - [Project Settings...] from the main menu.
2.Select the Time periods tab from the properties window.
3.Specify 9:00 for the property "Day demarcation time".
Q:How to specify a project name
A:
Steps:
1.Select [Schedule] - [Project Settings...] from the main menu.
2.In the properties window, select the Common tab and specify a name for the property "Alias".
Q:How to specify a method of calculating multiple setups
A:
Steps:
1.Click on the [Project Settings] button on the toolbar. Or, select [Schedule] - [Project Settings...] from the main menu. Properties of the project settings will be displayed in the properties window.
2.Select the Settings tab from the properties window. Properties of the settings will be displayed in the properties window.
3.Click the "Value" cell of the property "Setup time calculation method" and select the target value from the dropdown list box.