Q:How to specify the yield of a process
A:
Steps:
1.In the Integrated Master Editor, specify values in the "Yield rate" and "Scrap quantity" fields of the input instruction of the target process.
Q:How to specify that this process will start within 120 minutes after the end of the previous process
A:
Steps:
1.In the "Time constraint MAX" field of the Integrated Master Editor, specify "the maximum amount of time above which this process and the previous process should not be separated".
2.In the "Settings" tab of the Project Settings, check the property "Enable time constraint MAX".