How to specify inventory constraints for an item

Q:How to specify inventory constraints for an item

A:

Steps:

1.In the item table, select "Yes" from the dropdown list box of the property "Inventory constraint flag" of the target item.
2.When you want to enable inventory constraints for an item, you also need to make the same setting in the scheduling parameter settings.

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab of the properties window.
3.Check the property "Enable inventory constraints".

How to prevent auto-generated orders from producing a surplus in production quantities

Q:How to prevent auto-generated orders from producing a surplus in production quantities

A:

How to specify for an item that split operations will be performed in parallel

Q:How to specify for an item that split operations will be performed in parallel

A:

Steps:

1.Select [Table View] - [Item] from the menu bar. The item table will be displayed.
2.In the item table, specify a value in the "Split parallel number" field of the target item.
3.Display the resource Gantt chart and click on the [Reschedule] button. Split operations will be assigned in parallel to resources as many as the number you specified in the "Split parallel number" field.

How to specify a split ratio for an item by which to split an operation

Q:How to specify a split ratio for an item by which to split an operation

A:

Steps:

1.Select [Table View] - [Item] from the menu bar. The item table will be displayed.
2.In the item table, specify a split ratio by which to split an operation in the "Split ratio" field of the target item.
3.Display the resource Gantt chart and click on the [Reschedule] button. An operation will be split and assigned by the specified ratio.

How to specify a split number for an item by which to split an operation

Q:How to specify a split number for an item by which to split an operation

A:

Steps:

1.Select [Table View] - [Item] from the menu bar. The item table will be displayed.
2.In the item table, specify a split number by which to split an operation in the "Split number" field of the target item.
3.Display the resource Gantt chart and click on the [Reschedule] button. An operation will be split into the specified number and assigned.