APS (Advanced Planning and Scheduling) Asprova APS

 
Home > FAQChangeovers
FAQ

Changeovers

Search in FAQ:

How to specify a setup time for changing an item

Q:How to specify a setup time for changing an item

A:

Steps:

1,In the item setup table, specify the resource that requires a setup in the "Resource" field.
2,In the "Item L" and "Item R" fields of the same table, specify a combination of items.
3,In the "Setup time" field of the same table, specify a setup time in minutes.

How to specify a setup time for changing a spec

Q:How to specify a setup time for changing a spec

A:

Steps:

1,In the spec n setup table, specify the resource that requires a setup in the "Resource" field.
2,In the "Previous spec" and "Next spec" fields of the same table, specify a combination of specs.
3,In the "Setup time" field of the same table, specify a setup time in minutes. *n=1,2,3,

How to specify a setup time for changing a sub resource

Q:How to specify a setup time for changing a sub resource

A:

Steps:

1,In the resource setup table, specify the resource that requires a setup in the "Resource" field.
2,In the "Resource L" and "Resource R" fields of the same table, enter a combination of resources.
3,In the "Setup time" field of the same table, specify a setup time in minutes.

How to display a changeover even when there are no previous operations

Q:How to display a changeover even when there are no previous operations

A:

Steps:

1,In each setup table, specify "!" for the property "Item L", "Resource L", or "Previous spec".
2,When no left operations exist, the setup time of the record for which "!" is specified will be used.
3,You can make the above setting only for "Item L", "Resource L", or "Previous spec".
4,No left operation means that there is actually no use instruction for that resource in the infinite past.