Changing the size of the dropdown list box of the scheduling parameter

Q:The name of the scheduling parameter is to long to be displayed all in the dropdown list box.How to make the dropdown list box longer.

A:

Yes.

Select [Tools] - [Customize] from the menu bar.The Customize dialog is displayed.Select the "setting" in the "Command" tab. the dropdown list box of the scheduling parameter is displayed. Return the dropdown list being displayed in the toolbar, appropriate the cursor to the pool of it, and the size of the cursor will be changed longer of shorter.

The sequence of the registered order when use the auto-replenishment

Q:The order is put in from XXXXXX0009 to XXXXXX0013. The dispatching rule is specified as "Order code"to "Ascending". The item is set "Auto-replenish flag" to "Yes". Then schedule it in the forward , and order M00104 and M00105 will be made in the replenishment order.The sequence of the order is not rowed in the dispatching rule (XXXXXX0010 is in the front and XXXXXX0009 is behind ) How to let it as the rule.By the way,setting "Auto-replenish flag" to "Yes"(One-to-one production), the sequence of the order is rowed in the order code.In addition, can be Auto-replenished without chenging the sequence of the order (the item replenished can't be settled. )

A:

As you know , when reassigned in the forward ,you need to reassign the replenishment order first than the registered order.So when reassign the replenishment order , you must to set it as the dispatching rule of the code of the pegged registered order.So we specify a expression as follows
Min(ME.Order.RightmostOrder,TARGET.Code)
Now compare with the code of the pegged the rightmost orders ,the character code will be dispatched from the small one.

the answer for the second qustion,do not make it to the operation which you don't want to change in the filter operations . That means needn't cancel the reassign if you don't want to change it.And just cancel the reassignment of replenishment order and made it to be auto-replenished.

How to assign all target orders forward

Q:How to assign all target orders forward

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Assignment direction" and select "Forward" from the dropdown list box.

* When time fixed levels are specified, orders will be assigned according to the settings of the time fixed levels.

How to assign all target orders backward

Q:How to assign all target orders backward

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Assignment direction" and select "Backward" from the dropdown list box.

* When time fixed levels are specified, orders will be assigned according to the settings of the time fixed levels.

How to perform finite capacity scheduling

Q:How to perform finite capacity scheduling

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Assignment type" and select "Finite capacity" from the dropdown list box.

How to perform infinite capacity scheduling

Q:How to perform infinite capacity scheduling

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Assignment type" and select "Infinite capacity" from the dropdown list box.

How to filter orders to assign

Q:How to filter orders to assign

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the Filter tab from the properties window. Properties related to filtering will be displayed in the properties window.
3.Click on the [...] button for the property "Filter orders". The Filter orders dialog will be displayed.
4.In this dialog, specify a condition(s) by which you want to filter orders.

In the Filter orders dialog, you can use properties existing in the order class as they are.

You can also filter orders using low level codes. Only in that case, please use the properties "Low level code MIN" and "Low level code MAX" of the scheduling parameter instead of the Filter dialog.

How to specify an assignment period

Q:How to specify an assignment period

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the Time periods tab from the properties window. Properties related to time periods will be displayed in the properties window.
3.Specify values for the properties "Assignment start time" and "Assignment end time".

How to specify to temporarily fix certain operations during scheduling

Q:How to specify to temporarily fix certain operations during scheduling

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Temporary operation fix" and select a target value from the dropdown list box.

How to assign operations to the resource with the highest resource priority

Q:How to assign operations to the resource with the highest resource priority

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Resource selection method" and select "Priority resource" from the dropdown list box.

How to specify to consider capacity values of sub resources in calculating production times

Q:How to specify to consider capacity values of sub resources in calculating production times

A:

Steps:

1.Click on the [Scheduling Parameter Settings] button on the toolbar. Or, select [Schedule] - [Scheduling Parameter Settings...] from the main menu. Properties of the current scheduling parameter will be displayed in the properties window.
2.Select the General tab from the properties window.
3.Click the Value cell of the property "Production time calculation" and select "Longest time sub resource" from the dropdown list box.