Ver.9.0.1 Resource lock can now be specified in Master use instructions of the Integrated Master.

Resource lock can now be specified in Master use instructions of the Integrated Master.
This makes it possible to lock resources according to the combination of items and resources.
As shown in the following example, Equipment3 does not use a truck, but the previous and the next processes use a truck to move items. Therefore, by locking the resource in the Integrated Master, the truck can be properly locked (assigned).

Resource Lock Option

The following example sets a resource lock on the resource (truck). Since a lock is applied to a section that actually does not need it, assignment cannot be made properly.

Resource Lock Option

Resource lock
  Asprova Help -> [Option]-[Resource Lock Option] – HelpNo.:749000