How to specify a setup time factor

Steps:

In the resource table, enter a setup time factor in the “Setup time factor” field of the target resource.
1.The followings are the relationships between values you specify as setup time factors and production times:
Setup time factor Meanings
0: Regards as 1.
Greater than 0 and smaller than 1: Indicates a lower efficiency than normal. The setup time will increase.
1: 100%. The setup time will not change.
Greater than 1: Indicates a higher efficiency than normal. The setup time will decrease.