How to schedule metal molds and jigs

Steps:

1.Select the Integrated Master.
2.Add a use instruction to the process in which a metal mold is used.
3.Specify “S0” in the “Instruction code” field.
4.Specify the resource code of the metal mold in the “Resource/Item” field.
5.Specify “0” in the “Production” field.

* For the instruction code “S0”, 10 codes from S0 to S9 are recognized as sub resources by default.
You can also use other strings for sub resources by changing the settings of the use instruction master.